Showing posts with label plumbing. Show all posts
Showing posts with label plumbing. Show all posts

Saturday, January 8, 2011

Status Report

Work on the new home is nearing completion. The primary holdup is the concrete work for the driveway, front walk, and east side pad. The landscaper needs to complete a paving stone patio and walk in back. The weather has either been too cold or too wet to permit the work to proceed.

We also need stairs built for garage and deck entry.



Need to have a concrete walk laid up to fence line in back.
Electrical work needs to be completed. The light fixture outside the garage door needs to be changed, a blank needs to be installed for the great room light switch, and a number of outlet covers need to be installed. Light fixtures above vanity in powder room are crooked and need adjustment.

An additional outlet has been installed in the hall bathroom. According to Todd of Silverline Electric, the circuit for the bathroom will handle 1440 watts. Our current space heater pulls 1320, so we'll have to get a smaller heater. The 3rd pendant line has been installed in the main kitchen, and an additional switch has been installed for the can lights over the downstairs kitchenette. The LED covers have been changed.





There's still work to be done in the storage room, including installing the vent cover, wrapping the furnace ductwork, and covering a hole in the ceiling.




Trim around fireplace needs to be reattached, and floorboard in front of hearth needs to be installed.

Toilet seat in hall bath is missing.
Temporary shower panel for hall bath remains to be installed.
Touch up painting remains to be done (paint cans in utility room).
Talon Homes, Inc. performed a thorough walkthrough to identify drywall repair and touch up painting required.

Chip Grisham, Talon Homes, Inc.

Mike Creamer, Talon Homes, Inc.
Atrium delivered window screens Thursday. They are stored in the garage. Also in the garage are excess light fixtures that KIE needs to pick up.

There's some hardware (e.g., mudroom closet door pulls) that needs to be attached.

There are items in the garage that need to be retrieved (e.g., old kitchen window, lumber).

Northwood is scheduled to do their "bump and adjust" on the cabinets next Tuesday, the 11th.



Northwood will add hole and grommet to desk to allow electrical/phone wires.
Other fixes are shown in the photos below. Cleaners are working at the house this weekend and any further work in the house may require that they return. Subs should be instructed that shoe/boot covers are mandatory. Laying cardboard will not suffice. Painters should use measures (tarp, tape) to avoid spills.

Access door in master WIC needs to have a handle attached.
Talon is going to arrange to have a lattice work fence built to protect the compressor wire by the deck.
Stuccoed deck posts need to be painted.
Some laminate flooring is not flush. The gaps need to be filled/caulked somehow.
Washer drain needs to be installed.
Bottom of door frames in places not flush with flooring (this is entry to master WIC).


Monday, December 6, 2010

Sink & Shower Installation, 12/6/2010

Kitchen sink

Camerist integrated faucet

Wet bar sink

Camerist no-spray faucet

Master bathroom sinks

Hall bathroom sink

Downstairs bathroom sink

Powder room sink

Hall bathroom shower

Master bathroom shower

Thursday, September 30, 2010

Central Vacuum System Rough In

Silverline Electric roughed in the plumbing for a central vac system this week. This involves a considerable amount of piping running from the floor outlets up the walls to the attic. We're having the plumbing installed for the central vac, but will hold off on installing a vacuum receptacle and power unit until we decide we need an operational system.
Central vac outlet in hall near master and hall bedrooms.

Pipe runs for central vac are in attic.



Central vac plumbing on lower level ceiling along HVAC ductwork.

Central Vac outlet in lower level hall.


 The photo below is taken looking up from the lower level to the point where the central vac outlet in the main floor kitchen exits through the floor to the lower level vacuum plumbing.

Here's the hose and fixture for the central vac outlet in the kitchen. It will go under the peninsula.

Sunday, September 26, 2010

Tankless Hot Water System and Sewer System Plumbing

These pipes under the deck appeared Wednesday or Thursday last week. Eventually, a chase (i.e., box) will be built to hide these pipes.

 One is apparently a exhaust line for the tankless hot water, and the other would be the intake.

 The exhaust travels up the back of the garage,

 and vents on the east side of the roof.

 The pipes begin in the lower level storage room where the tankless system will be located.

There's another piece of large diameter pipe right under the Bedroom #3 west window

This is apparently a sewer clean out. This eyesore will be cut down closer to ground level and covered with a lidded box.